Project Name: NWTP Pond Constuction

Subcontract Name: Subcontract for FRP of discharge Structure on BC-IX Pond
Client: Shamrock Civil/Golder JV
Main Contract Value: $500M
Subcontract Value: $1M

Bampak were awarded contract to complete full FRP of the Discharge Structure as part of the the Northern Waters Treatment plant at Woleebee Creek. Bampak completed the contract works to a tight schedule and completed on time early in 2015.